Gas Transmission Project HANS

Location: Bernau–Szczecin

Total technical output: 3.0–5.0 bcm per year

Total length: 150 km

Planned commissioning: 2018

Special purpose vehicles implementing the project: PPG Polska Sp. z o.o and PPG Pipeline Projektgesellschaft mbH

The Hans Project is a project covering construction of gas pipeline Bernau-Szczecin, which will connect Polish gas market with the network of gas pipelines in the western Europe. The pipeline will provide access to import utilities from Germany. Total technical output of the gas pipeline is 3.0 – 5.0 bcm per year. Its total length (150 km) shall include a 30 km section in Poland and 120 km in Germany.

Strategic partners will be invited to collaborate in development of the project in Poland and Germany in 2014. We have already obtained a construction permit for the Bernau-Szczecin gas pipeline and secured an attractive model of settlement of accounts based on RAB (regulatory asset base). The project is planned to be completed and commissioned in 2018.


Bernau - Szczecin pipeline

Total technical capacity3.0 - 5.0 bcm p.a.
Compresssor stations1 x 5.4 MW
Lenghtc. 150 km (30km in POL, 120 km in GER)
Start of construction2015
Start of operations2018

 Project Status

FEED DesignSecured
Construction PermitsSecured
Rights of Wayc. 50% Secured
Exemption from TPA/UnbundlingIn progress
Commercial closingIn progress
Grid connectionIn progress
EPCTo be completed
FinancingTo be completed