PV Sulechów 2

Location: Kruszyna, commune of Sulechów

Voivodeship: lubuskie

Total PV Farm power: 11,714 MWp

 

On 26 November 2020, based on the announcement about the auction of 1 October 2020, the auction for sale of electricity from renewable sources, AZ/7/2020, was held. All projects submitted by Polenergia S.A. won this year’s RES auctions for new photovoltaic plants. 15-year support will go to the PV project portfolio: Sulechów 2, Sulechów 3 and Buk 1 with a total capacity of 28 MW.

The Sulechów 2 photovoltaic plant project is implemented by SPV Polenergia Farma Wiatrowa 17 Sp. z o.o. Sulechów 2 will be located on plots of land 124/4, 124/3, 142, 141, 8/28, 8/15 and on portions of plots 120/8, 120/5, 121/3, 122/3, 123/3 in the district of Kruszyna, in the Sulechów gmina, in the Zielona Góra poviat in the Lubuskie Province.

The Sulechów 2 photovoltaic plant will comprise twelve photovoltaic farms with a capacity up to 1 MW each with the necessary technical infrastructure. The total capacity of wind farms will be 11.714 MWp. The environmental impact assessment procedure for Sulechów 2 was carried out by the competent authority, namely the Mayor of Sulechów. No necessity of carrying out environmental impact assessment for the planned project was determined. During the environmental impact assessment procedure, the State Sanitary Inspector, the State Water Holding “Wody Polskie” and the Regional Environmental Protection Directorate in Gorzów Wielkopolski were consulted, in line with the requirements of the environmental protection law. The procedure also allowed for the participation of stakeholders. The procedure ended with issue of a decision on environmental constraints (document No. GKR.6220.17.2018.MG on 18 October 2018) permitting the construction and assembly of thirteen photovoltaic farms with a capacity up to 1 MW each with the necessary technical infrastructure, with the staging of works. Building permit has also been obtained for the project.

Scheduled start of the construction work is June 2021.

 